Successful Completion of Commissioning for FEEDER2 Vessel's Hybrid Scrubber System (EGCS)

  Recently, the FEEDER2 ship in Guangzhou, China successfully completed the commissioning of the hybrid scrubber system. This project was carried out by engineers dispatched by Wahtung.

The installation progress, including cable connection, power testing, parameter setting, program import, system operation, inspection, and trial voyage, was carried out steadily at each stage. From the tower structure inside and outside, the layout of pipelines, to the remote control of valves and the motors of pumps, every step was meticulously executed.

Identifying issues and resolving them. From checking if the motor rotation is correct, ensuring there are no leaks in the tower's pipelines, to testing the insulation of the system and all sensors. Despite the high temperature weather, the system operated smoothly, allowing the project to be successfully completed. Making everything worthwhile!